Following are the findings of a pre-feasibility study of Submarine cable interconnection in greater Male region (stretching from Thilafushi to Hulhumale) in 2010. A detail feasibility study is still pending for this huge investment with negligible financial return. But it is an investment that is desperately needed for continued power supply with in next couple of years.
Greater Male Region:
- Thilafushi – Villigili :
3.4km, Villigili – Male: 1.5km, Male – Hulhumale: 1km
- Installed total capacity in
the Male region: 46.16MW, with
dependable capacity of 41.544MW
- Thilafushi has private
power producers in addition to STELCO plant
- In 2009 demand load
in Male’ rose beyond the dependable capacity
- The demand growth of the
region is approximately 11% per year
- Even with the
addition of the 3x8MW diesel units in 2010 and 2011, Male’ would run out of
capacity by 2015 as the older units start to retire.
- The rapid pace of
development on Hulhumale’ will use up the available supply capacity by 2010 and
significant generation additions would be required
- Villigili has sufficient to
last until 2020 when the existing units will start to be retired
- Thilafushi will run out
of capacity in 2010 and generation
additions will be required to meet both only the growth of the existing load
but also to take over the industrial load now served by captive generation
- Three options for
interconnection were suggested and tentative price was estimated
- Scenario 1: Build
generation capacity in Hulhumale for the future demand of Thilafushi,
Villigili, Male and Hulhumale’ (which would amount to additional 110MW build up
in Hulhumale by 2030 while most generators in other islands would retire). The connections are made by laying dual cable
as a fail safe.
- Scenario 2: Build
generation capacity in Hulhumale and Thilafushi for the future demand of
Thilafushi, Villigili, Male and Hulhumale’ (which would amount to additional
63.2MW build up in Hulhumale and 46.8MW in Thilafushi by 2030 while most
generators in other islands would retire). The connections are made by laying
dual cable as a fail safe.
- Scenario 3: Build
generation capacity in Hulhumale and Thilafushi for the future demand of
Thilafushi, Villigili, Male and Hulhumale’ (which would amount to additional
77.6MW build up in Hulhumale and 46.8MW in Thilafushi by 2030 while most
generators in other islands would retire).
- Cost of scenario 1
and 2 is estimated to be USD 63.3 Million
- Cost Scenario 3 is
estimated to be USD 43.7 Million, but this scenario requires additional
installation of 16 MW in each island in case of cable outage. This is an
additional capital cost of about USD 40 million.
- 5 US cents increase in
tariff for transmission system to cover capital cost as well as O&M cost
Environmental considerations:
·
There is no significant
environmental impact if the project proceeds with the proper regulations and
conditions. Environmentally it helps by optimizing power generation
efficiency and helps towards carbon neutrality by providing more opportunities
for different RE power generation considered in Carbon Neutral paper. Calculations
in Carbon Neutral Paper by Dan Morrel (which was used as a basis of carbon neutrality policy
announcement) was revised from USD 1.1 Billion to USD 2.3 Billion